BEST RERA ADVOCATE ,LAWYERS & CONSULTANTS

  • HOME
  • SERVICES
  • ABOUT US
  • CONTACT US
  • PAN INDIA OFFICES
  • RERA Judgements
  • AGENT REGISTRATION
  • PROJECT REGISTRATION
  • PARTNER WITH US
  • Project Investigation
  • RERA JUDGEMENTS LINKS
  • Blogs
  • More
    • HOME
    • SERVICES
    • ABOUT US
    • CONTACT US
    • PAN INDIA OFFICES
    • RERA Judgements
    • AGENT REGISTRATION
    • PROJECT REGISTRATION
    • PARTNER WITH US
    • Project Investigation
    • RERA JUDGEMENTS LINKS
    • Blogs
  • Sign In

  • My Account
  • Signed in as:

  • filler@godaddy.com


  • My Account
  • Sign out


Signed in as:

filler@godaddy.com

  • HOME
  • SERVICES
  • ABOUT US
  • CONTACT US
  • PAN INDIA OFFICES
  • RERA Judgements
  • AGENT REGISTRATION
  • PROJECT REGISTRATION
  • PARTNER WITH US
  • Project Investigation
  • RERA JUDGEMENTS LINKS
  • Blogs

Account


  • My Account
  • Sign out


  • Sign In
  • My Account

Important RERA judgement

RERA appeal lawyer

Allotte can't be compelled to take possession without occupation certificate after expiry of stipulated period

Pioneer Urban Land & Infrastructure Ltd. vs Govindan Raghavan Civil Appeal No. 12238 OF 2018   If Builder failed to fulfill his contractual obligation of obtaining the  Certificate and offering possession of the flat to the  Purchaser  within the time stipulated in the Agreement, the Flat Purchaser could not be compelled to take possessio

Pioneer Urban Land & Infrastructure Ltd. vs Govindan Raghavan Civil Appeal No. 12238 OF 2018   If Builder failed to fulfill his contractual obligation of obtaining the  Certificate and offering possession of the flat to the  Purchaser  within the time stipulated in the Agreement, the Flat Purchaser could not be compelled to take possession, flat Purchaser  entitled to  the  refund of the entire amount deposited with Interest  

Contact Us
Consumer Court vs. RERA legal advice

Manifestly unreasonable to construe the contract between the parties as requiring the buyer to wait

1. 2019 -Hon’ble Supreme Court of India  in Kolkata West International City Pvt. Ltd. Vs. Devasis Rudra, II (2019) CPJ 29 SC, in which the Hon’ble Apex Court has observed as hereunder: “.....It would be manifestly unreasonable to construe the contract between the parties as requiring the buyer to wait indefinitely for possession. By 2016,

1. 2019 -Hon’ble Supreme Court of India  in Kolkata West International City Pvt. Ltd. Vs. Devasis Rudra, II (2019) CPJ 29 SC, in which the Hon’ble Apex Court has observed as hereunder: “.....It would be manifestly unreasonable to construe the contract between the parties as requiring the buyer to wait indefinitely for possession. By 2016, nearly seven years had elapsed from the date of the agreement. Even according to the developer, the completion certificate was received on 29 March 2016. This was nearly seven years after the extended date for the handing over of possession prescribed by the agreement. A buyer can be expected to wait for possession for a reasonable period. A period of seven years in beyond what is reasonable. Hence, it would have been manifestly unfair to non-suit the buyer merely on the basis of the first prayer in the reliefs sought before the SCDRC. There was in any event a prayer for refund. 

Contact Us
RERA consultant for developers

Possession not delivered within the specified time, allottee is entitled to a refund

Builder cannot demand full payment if the Project's Occupancy Certificate is not obtained

 Bangalore Development Authority v. Syndicate Bank(2007) 6 SCC 71 

Coordinate Bench of Supreme court  held that when possession of the allotted plot/flat/house is not delivered within the specified time, the allottee is entitled to a refund of the amount paid, with reasonable Interest thereon from the date of payment till the date of refund. 

Contact Us
RERA advocate for project registration

Builder cannot demand full payment if the Project's Occupancy Certificate is not obtained

Builder cannot demand full payment if the Project's Occupancy Certificate is not obtained

Builder cannot demand full payment if the Project's Occupancy Certificate is not obtained

 HP RERA  has held that a builder cannot demand full payment from the homebuyer if the Project's Occupancy Certificate has not been obtained and the construction of the flat is not complete within the agreed time for delivery of possession   

Contact Us
RERA lawyer for real estate litigation

Builders can't use 70% of buyers fund to repay bank loan

Builder cannot demand full payment if the Project's Occupancy Certificate is not obtained

Builders can't use 70% of buyers fund to repay bank loan

 This is the latest direction issued by RERA  UP/Gurugram Directing developers can't use 70% of the money collected for buyers to reply the bank loan, the amount is for completion of construction only    

Contact Us
Advocate for RERA complaint filing

RERA JUDGEMENTS LINKS

Builder cannot demand full payment if the Project's Occupancy Certificate is not obtained

Builders can't use 70% of buyers fund to repay bank loan

RERA Andaman Nicobar, RERA Bihar, RERA Chandigarh, RERA Delhi, RERA Dehradun, RERA Gurugram, RERA Gujarat, RERA Goa, RERA Himachal, RERA Jaipur, RERA Karnataka,  RERA Maharashtra, RERA Madhya Pradesh 

RERA  Panchkula, RERA Punjab, RERA Tamil Nadu, RERA Telangana, RERA UP 

RERA Judgement PAN INDIA

RERA judgement at glance

Builder cannot demand full payment if the Project's Occupancy Certificate is not obtained

Allotte can't be compelled to take possession without occupation certificate after expiry of stipulated period

RERA advocate for homebuyers

HP RERA  has held that a builder cannot demand full payment from the homebuyer if the Project's Occupancy Certificate has not been obtained and the construction of the flat is not complete within the agreed time for delivery of possession  


Allotte can't be compelled to take possession without occupation certificate after expiry of stipulated period

Allotte can't be compelled to take possession without occupation certificate after expiry of stipulated period

Experienced RERA advocate in Gurugram

 Pioneer Urban Land & Infrastructure Ltd. vs Govindan Raghavan Civil Appeal No. 12238 OF 2018   If Builder failed to fulfill his contractual obligation of obtaining the  Certificate and offering possession of the flat to the  Purchaser  within the time stipulated in the Agreement, the Flat Purchaser could not be compelled to take possession, flat Purchaser  entitled to  the  refund of the entire amount deposited with Interest 


Possession not delivered within the specified time, allottee is entitled to a refund

RERA lawyer for delayed possession cases

  Bangalore Development Authority v. Syndicate Bank(2007) 6 SCC 71 

Coordinate Bench of Supreme court  held that when possession of the allotted plot/flat/house is not delivered within the specified time, the allottee is entitled to a refund of the amount paid, with reasonable Interest thereon from the date of payment till the date of refund. 

Manifestly unreasonable to construe the contract between the parties as requiring the buyer to wait

RERA Advocate for builder-buyer dispute

  1. 2019 -Hon’ble Supreme Court of India  in Kolkata West International City Pvt. Ltd. Vs. Devasis Rudra, II (2019) CPJ 29 SC, in which the Hon’ble Apex Court has observed as hereunder: “.....It would be manifestly unreasonable to construe the contract between the parties as requiring the buyer to wait indefinitely for possession. By 2016, nearly seven years had elapsed from the date of the agreement. Even according to the developer, the completion certificate was received on 29 March 2016. This was nearly seven years after the extended date for the handing over of possession prescribed by the agreement. A buyer can be expected to wait for possession for a reasonable period. A period of seven years in beyond what is reasonable. Hence, it would have been manifestly unfair to non-suit the buyer merely on the basis of the first prayer in the reliefs sought before the SCDRC. There was in any event a prayer for refund.

Builders can't use 70% of buyers fund to repay bank loan

Builders can't use 70% of buyers fund to repay bank loan

RERA Dispute Lawyer

This is the latest direction issued by RERA  UP/Gurugram Directing developers can't use 70% of the money collected for buyers to reply the bank loan, the amount is for completion of construction only   

RERA Judgement PAN INDIA

RERA JUDGEMENTS LINKS

Builders can't use 70% of buyers fund to repay bank loan

RERA Advocates

RERA Andaman Nicobar

RERA Bihar

RERA Chandigarh

RERA Delhi

RERA Dehradun

RERA Gurugram 

RERA Gujarat

RERA Goa 

RERA Himachal

RERA Jaipur

RERA Karnataka

 RERA Maharashtra 

RERA Madhya Pradesh 

RERA  Panchkula

RERA Punjab

RERA Tamil Nadu

RERA Telangana

RERA UP 



RERA Judgement PAN INDIA

RERA News updates - for information only

As Reported in Public domain

  • NBW issed agaisnt 86 buides by RERA Court Gurugram 
  • Jaypee Kalypso Court: RERA  assisted the buyers to Get A Disputed Realty Project Completed In Noida Within Two Years
  • Home buyer can seek protection under REREA  , agaisnt  Banks , for non payment of loan by builders 
  • under agreement . The RERA Prevails Over SARFAESI Act   : Supreme Court  
  • Builder directed  to pay home buyers assured returns 
  • Haryana Real Estate Regulator Authority’s (H-Rera) Gurugram holds developer cannot deny  assured return to the investors and walk away from the contractual obligation or cite a new RERA Law being put to operation in 2016.
  • Rera court directs  developer to pay INR 2  crore for failing to develop flats in time
  • Homebuyers entitled to ‘just and reasonable' compensation for delay in possession: Supremecourt 
  • Delayed handing over of possession amounts to ‘deficiency’; flat buyers entitled to compensation: SC Wg. Cdr. Arifur Rahman Kan and Aleya Sultana v. DLF Southern Homes Pvt Ltd, Civil Appeal No. 6239 of 2019, decided on 24.08.2020
  • NCDRC orders developers in Gurgaon real estate projects to refund Rs 12 crore to homebuyers; 
  • disposes of 25 cases
  • UP RERA slaps  ₹2.5 crore penalty on 11 developers for non-compliance - 
  • Don’t charge buyers till homes completed, RERA Gurugram 
  • Flats not ready in time, Rera Gurugram  asks developer to pay Rs 2 cro ..
  • UP rera  -impose penalty on supertech for delay in deliver of 7000 flated
  • Gurugram: Two builders told to fully refund 5 flat buyers, 
  •  Sector-37C in Gurugram, promoted by Ramprastha Promoters and ..

Legal expert for RERA compliance

LATEST  RERA  NEWS 

judgements on possession

Real estate litigation attorney

Complainants cannot be made to wait indefinitely as the possession

National commission New Delhi in consumer caseno. 2923 of 2017  titled Visheshsood & Another. versus Raheja developers limited  dated 15.11.2019  held that the Complainants cannot be made to wait indefinitely as the possession of the unit has not been handed over so far. Therefore, we are of the considered view that the Complainants are entitled for refund of the principal amount with reasonable interest.  

Failure to obtain the completion certificate in time Purchaser can’t be compelled to take possessio

 Supreme Court of India Pioneer Urban Land And ... vs Govindan Raghavan on 2 April, 2019CIVIL APPEAL NO. 12238 OF 2018  

The Appellant Builder failed to fulfill his contractual obligation of obtaining the Occupancy Certificate and offering possession of the flat to the Respondent Purchaser within the time stipulated in the Agreement, or within a reasonable time thereafter. The Respondent Flat Purchaser could not be compelled to take possession of the flat, even though it was offered almost 2 years after the grace period under the Agreement expired. In these circumstances, the Respondent Flat Purchaser was entitled to be granted the relief prayed for i.e. refund of the entire amount deposited by him with Interest 

Supreme court of India M/S Treaty Construction vs M/S Ruby Tower Co Op Hsg. Society ... On 19 July,

 Cearly, not obtaining occupancy certificate is the deficiency on the part of the OP/appellant.( builder ) Therefore, it is necessary to direct the OP to obtain the Occupancy Certificate in a time bound manner. In this respect, the order of the State Commission is perfectly valid so far as it relates to directing the OP to obtain Occupancy Certificate within 90 days. Once the Occupancy Certificate is obtained the title has to be conveyed to the Society within four months and in any case, non-compliance with the conditions to obtain Occupancy Certificate speaks volumes about the deficiency of services on the part of the appellants 

One sided agreement

 Supreme Court of India  in Pioneer Urban Land & Infrastructure Ltd. Vs. Govindan Raghavan, II (2009) CPJ 34 (SC), wherein the Apex Court has observed as follows: “6.7.

A terms of a contract will not be final and binding if it is shown that the flat purchasers had no option but to sign on the dotted line, on a contract framed by the builder. The contractual terms of the Agreement dated 08.05.2012 are ex-facie one sided, unfair and unreasonable. The incorporation of such one-sided clauses in an agreementconstitutes an unfair trade practice as per Section 2(r) of the Consumer Protection Act, 1986 since it adopts unfair methods or practices for the purpose of selling the flats by the Builder. 7. In view of the above discussion, we have no hesitation in holding that the terms of the Apartment Buyer’s Agreement dated 08.05.2012 were wholly one-sided and unfair to the Respondent-Flat Purchaser. The Appellant-Builder cannot seek to bind the Respondent with such one-sided contractual terms.

Concurrent Jurisdiction of Consumer court

Hon’ble Supreme Court in Pioneer Urban Land and Infrastructure Ltd. &Anr. Vs. Union of India &Ors . - 2019 SCC Online SC 1005, has held that remedies given to the allottees of the flats/apartments are concurrent and such allottees are in a position to avail of remedies under the Consumer Protection Act, RERA, as well as trigger the provisions of the Insolvency and Bankruptcy Code, 2016.

One sided agreement 

Builder to pay Compensation and interest to buyers for delay in possession

DLF SOUTHERN HOMES PVT. LTD V/S M/S ANNABELL BUILDERS DEVELOPERS” the apex court has held that delay in possession of flat amounts to deficiency in service and builder is liable to make payment to the home buyers on cost of flat for the period of delay in delivery in addition to meager amount of compensation as mentioned in apartment buyer agreement. The court said the flat purchaser suffer agony and harassment as a result of default of developer. Flat purchaser make legitimate assessment in regard to future course of their lives based on flat which has been purchased being available being for use and occupation. The legitimate expectation are belied when developer fails to fulfill contractual obligation.

Contact us

judgements on possession

RERA Lawyers in India

Complainants cannot be made to wait indefinitely as the possession

 National commission New Delhi in consumer caseno. 2923 of 2017  titled Visheshsood & Another. versus Raheja developers limited  dated 15.11.2019  held that the Complainants cannot be made to wait indefinitely as the possession of the unit has not been handed over so far. Therefore, we are of the considered view that the Complainants are entitled for refund of the principal amount with reasonable interest.   

Contact Us
RERA Legal Services

Failure to obtain the completion certificate in time Purchaser can’t be compelled to take possessio

Supreme Court of India Pioneer Urban Land And ... vs Govindan Raghavan on 2 April, 2019CIVIL APPEAL NO. 12238 OF 2018  

The Appellant Builder failed to fulfill his contractual obligation of obtaining the Occupancy Certificate and offering possession of the flat to the Respondent Purchaser within the time stipulated in the Agreement, or within a reasonable time thereafter. The Respondent Flat Purchaser could not be compelled to take possession of the flat, even though it was offered almost 2 years after the grace period under the Agreement expired. In these circumstances, the Respondent Flat Purchaser was entitled to be granted the relief prayed for i.e. refund of the entire amount deposited by him with Interest 

Contact Us
File RERA Complaint Online

Supreme court of India M/S Treaty Construction vs M/S Ruby Tower Co Op Hsg. Society ... On 19 July,

 Cearly, not obtaining occupancy certificate is the deficiency on the part of the OP/appellant.( builder ) Therefore, it is necessary to direct the OP to obtain the Occupancy Certificate in a time bound manner. In this respect, the order of the State Commission is perfectly valid so far as it relates to directing the OP to obtain Occupancy Certificate within 90 days. Once the Occupancy Certificate is obtained the title has to be conveyed to the Society within four months and in any case, non-compliance with the conditions to obtain Occupancy Certificate speaks volumes about the deficiency of services on the part of the appellants  

Contact Us
RERA Dispute Resolution Lawyers

One sided agreement

Supreme Court of India  in Pioneer Urban Land & Infrastructure Ltd. Vs. Govindan Raghavan, II (2009) CPJ 34 (SC), wherein the Apex Court has observed as follows: “6.7.

A terms of a contract will not be final and binding if it is shown that the flat purchasers had no option but to sign on the dotted line, on a contract framed by the builder. The contractual terms of the Agreement dated 08.05.2012 are ex-facie one sided, unfair and unreasonable. The incorporation of such one-sided clauses in an agreementconstitutes an unfair trade practice as per Section 2(r) of the Consumer Protection Act, 1986 since it adopts unfair methods or practices for the purpose of selling the flats by the Builder. 7. In view of the above discussion, we have no hesitation in holding that the terms of the Apartment Buyer’s Agreement dated 08.05.2012 were wholly one-sided and unfair to the Respondent-Flat Purchaser. The Appellant-Builder cannot seek to bind the Respondent with such one-sided contractual terms.

Contact US
RERA Legal Help for Homebuyers

Concurrent Jurisdiction of Consumer court

 Hon’ble Supreme Court in Pioneer Urban Land and Infrastructure Ltd. &Anr. Vs. Union of India &Ors . - 2019 SCC Online SC 1005, has held that remedies given to the allottees of the flats/apartments are concurrent and such allottees are in a position to avail of remedies under the Consumer Protection Act, RERA, as well as trigger the provisions of the Insolvency and Bankruptcy Code, 2016.

One sided agreement 

Contact Us
Best RERA Advocate Near Me

Builder to pay Compensation and interest to buyers for delay in possession

 DLF SOUTHERN HOMES PVT. LTD V/S M/S ANNABELL BUILDERS DEVELOPERS” the apex court has held that delay in possession of flat amounts to deficiency in service and builder is liable to make payment to the home buyers on cost of flat for the period of delay in delivery in addition to meager amount of compensation as mentioned in apartment buyer agreement. The court said the flat purchaser suffer agony and harassment as a result of default of developer. Flat purchaser make legitimate assessment in regard to future course of their lives based on flat which has been purchased being available being for use and occupation. The legitimate expectation are belied when developer fails to fulfill contractual obligation. 

Contact Us

My Blog

Contact Us

Better yet, see us in person!

We love our customers, so feel free to visit during normal business hours.

Message us on WhatsApp

RERA ADVOCATES.COM

Plot no.285, Sector-14, Gurugram, HR 122001, IN

9810203697, 9990339922

Office Hours

Open today

09:00 am – 05:00 pm

Drop us a line!

This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.

Cancel
  • CONTACT US
  • RERA JUDGEMENTS LINKS

RERA ADVOCATES.COM

Plot no. 285, Sector-14, Gurugram, HR 122001, IN

9810203697 | 9990339922

 Copyright © 2025 All Rights Reserved Passion by  Rera Advocates.com

Powered by